Kenya's oldest geothermal plant is back. An additional 63.3 megawatts has been added to the national grid following the rehabilitation of Olkaria I.
The restoration marks a major step. The facility has been undergoing repairs for three years. It was first commissioned in 1981. The return comes as demand rises. More electricity is needed across the country. Concerns have also been raised over future supply.
Olkaria I completes major overhaul
The rehabilitation has now been completed. The announcement was made by Kenya Electricity Generating Company (KenGen). Managing Director Peter Njenga said the plant had previously generated about 45 megawatts before the works began.
The additional capacity has now been injected into the national grid. Testing is still being carried out ahead of the official commissioning. President William Ruto is expected to lead the ceremony on December 7, 2026.
"We are happy to announce that the rehabilitation works of Olkaria I are now complete, and we have injected an extra 63.3MW into the national grid," Njenga said.
The announcement was made in Naivasha. It followed a clean-up exercise ahead of a three-day sustainable energy conference in the Olkaria region.
KenGen seeks funding for new projects
Attention has also been turned to future investments. KenGen plans to use the conference to engage potential financiers. Several planned projects are expected to require substantial funding. The company intends to outline its plans and explain the resources needed.
"We are going to tell our financiers the projects that we are embarking on for the next number of years and the resources that we require," Njenga said.
He added that the company would showcase its achievements. The discussions are expected to help attract support for future energy developments.
Investors target Olkaria green energy park
Interest in the Olkaria green energy park is also growing. Five investors have already established a presence in the area, according to Njenga. He said sufficient geothermal energy was available. This was expected to support the needs of businesses planning to operate there.
A fertiliser manufacturing company was among the investors mentioned. It is expected to require 165 megawatts of geothermal energy. Njenga said the company would also use steam from geothermal fields.
"We have enough energy in Olkaria," he said.
He cited Kaishan as one of the companies involved in the planned industrial development.
Naivasha clean-up welcomed
The clean-up exercise was welcomed by youth leader Simon Wakaba. He said a cleaner environment would be essential as Naivasha pursued plans to become a resort city. Concerns over drainage were also raised. Wakaba argued that proper sanitation and waste management would be necessary to support the town's ambitions.
"We know what happens here in Naivasha in terms of drainage," he said.
He added that the town could not become a resort city without better drainage, cleanliness and environmental management.
The geothermal expansion and planned investments are expected to strengthen Olkaria's position as an energy and industrial centre. However, the long-term impact will depend on the successful completion of projects and the delivery of reliable power.